John F. Kennedy Blvd & Elk Grove Blvd Street Resurfacing Update - Expect Major Delays Beginning 9/24/18

Post Date:09/22/2018 2:57 PM

9/26/18 UPDATE: On Thursday, September 27, the roadway milling operations will be working on John F. Kennedy Blvd. between Arlington Heights Rd and Brantwood Ave.
  
9/25/18 UPDATE: On Wednesday, September 26 the roadway milling operations will be working on Elk Grove Blvd between Victoria Ln and Arlington Heights Rd.

9/24/18 UPDATE: On Tuesday, September 25 the roadway milling operations will be working on Elk Grove Blvd between Victoria Ln and Victoria Ln.

9/22/18 UPDATE: The pavement milling was delayed due to weather affecting the landscape work. The milling and resurfacing of Elk Grove Blvd (Arlington Heights Rd to Tonne Rd) and John F. Kennedy Blvd (Arlington Heights Rd to Brantwood Ave) is now scheduled to begin the week of September 24. 

MAJOR DELAYS are to be expected when traveling within the construction zone over the next few weeks.  In addition, motorists should anticipate traffic being controlled by construction flaggers, especially when milling operations are being completed at intersections. 

Construction will be scheduled to avoid the school drop off and pick up times, when possible. The Village will do its best to keep the inconvenience to a minimum.

Click here to view more information about the project.