News

Print
Press Enter to show all options, press Tab go to next option
    

John F. Kennedy Blvd & Elk Grove Blvd Street Resurfacing Update - Expect Major Delays Beginning 9/24/18

Post Date:09/22/2018 2:57 PM

UPDATE: The pavement milling was delayed due to weather affecting the landscape work. The milling and resurfacing of Elk Grove Blvd (Arlington Heights Rd to Tonne Rd) and John F. Kennedy Blvd (Arlington Heights Rd to Brantwood Ave) is now scheduled to begin the week of September 24. 

MAJOR DELAYS are to be expected when traveling within the construction zone over the next few weeks. Construction will be scheduled to avoid the school drop off and pick up times, when possible. The Village will do its best to keep the inconvenience to a minimum.

Click here to view more information about the project.
Return to full list >>