Project Update - July 2017

Beginning Monday, July 17, 2017, Lively Blvd will be closed to all traffic at the railroad crossing between Pratt Blvd and Arthur Ave. Swanson Contracting Co. will be reconstructing the railroad crossing and is scheduled to complete the project by Sunday, July 23, 2017, at which time Lively Blvd will be reopened to all traffic.  A detour will be posted throughout the area.

Week 7  

Project Overview

Beginning Monday, June 5, 2017, Swanson Contracting Co. will begin reconstructing twelve railroad crossings in the Elk Grove Business Park. These proposed railroad improvements will consist of the removal and replacement of the existing rail ties and ballast, and the installation of new continuous welded rails, and rubber or concrete panel interface with full depth asphalt crossing.

Rail crossing locations and dates for road closures are as follows:

Lively Blvd will be closed at the railroad crossing between Chase Ave and Touhy Ave from Monday, June 5th through Sunday, June 11th.

Lively Blvd will be closed at the railroad crossing between Touhy Ave and Estes Ave from Monday, June 12th through Sunday, June 18th.

Lively Blvd will be closed at the railroad crossing between Estes Ave and Greenleaf Ave from Monday, June 19th through Sunday, June 25th.

Lively Blvd will be closed at the railroad crossing between Greenleaf Ave and Lunt Ave from Monday, June 26th through Sunday, July 2nd .

Lively Blvd will be closed at the railroad crossing between Lunt Ave and Morse Ave from Monday, July 3rd through Sunday, July 9th.

Lively Blvd will be closed at the railroad crossing between Morse Ave and Pratt Blvd from Monday, 10th through Sunday, July 16th.

Lively Blvd will be closed at the railroad crossing between Pratt Blvd and Arthur Ave from Monday, July 17th through Sunday, July 23rd .

Pratt Blvd will be closed at the railroad crossing between Lively Blvd and Busse Rd from Monday, July 24th through Sunday, July 30th.

Greenleaf Ave will be closed at the railroad crossing between Nicholas Blvd and Elmhurst Rd from Monday, July 31st through Sunday, August 13th. (Two Week Road Closure)

Lunt Ave will be closed at the railroad crossing between Nicholas Blvd and Elmhurst Rd from Monday, August 14th through Sunday, August 27th. (Two Week Road Closure)

Pratt Blvd will be closed at the railroad crossing from Nicholas Blvd to Elmhurst Rd from Monday, August 28th through Sunday, September 3rd.

Arthur Ave will be closed at the railroad crossing from Nicholas Blvd to Elmhurst Rd from Monday, September 5th through Sunday, July 17th. (Two Week Road Closure)

Our goal is to complete this project with a minimum disruption to our business community.  We will do our best to keep your inconvenience to a minimum.  We thank you in advance for your patience and understanding.