Project Update - November 2017

The contractor is scheduled to place the final surface of pavement on Leicester Road on Wednesday, November 8th. This operation will be performed with the use of flaggers to ensure two-way traffic is maintained at all times. On Tuesday, November 7th the contractor will be placing primer, “fresh oil”, in preparation for Wednesday’s work.

To fix several reoccurring potholes adjacent to the crosswalks on Biesterfield Road the contractor removed an 2-foot wide strip of pavement adjacent to the crosswalks on Saturday, November 3rd.  Grindings were placed to fill the void until the final pavement can be placed on Tuesday, November 7th

In addition, the full closure of Leicester Road between the two Alexian Brothers entrances was reopened to two-way traffic on Saturday, November 4th.

Leicester Road Detour
Click for More Detail

Project Overview

This summer the will be reconstructing Leicester Road from Biesterfield Road north to Wellington Avenue as part of the Village’s long-range capital plan Elk Grove 2025: Investing for the Future.  The project is anticipated to begin in July and be completed by mid-November. The project includes full depth pavement removal and replacement, curb, sidewalk and driveway apron removal and replacement, new water main installation, repairs to the existing storm sewer system and landscaping restoration. The work will be staged to ensure access to Alexian Brothers Medical Center and residential properties remains available throughout the duration of the project.  Traffic detour signage will be posted to assist motorists around the construction. 

The project will be broken into 5 main stages as follows:
  • Stage 1 – Installation of the Water Main from Biesterfield Road to Wellington Avenue (Two-way traffic will be maintained)
  • Stage 2 – Reconstruction of Leicester Road from just south of Gloucester Drive to Wellington Avenue (Complete closure of Leicester Road from the Gloucester Dr to Wellington Ave including both intersections)
  • Stage 3a – Reconstruction of the west side of Leicester Road from Alexian Way to just south of Gloucester Drive (Northbound One-way Traffic Only.  Access to Alexian Brothers and Condominiums will be maintained.)
  • Stage 3b – Reconstruction of the east side of Leicester Road from Alexian Way to just south of Gloucester Drive (Northbound One-way Traffic Only.  Access to Alexian Brothers and Condominiums will be maintained.)
  • Stage 3c – Reconstruction of Leicester Road between the two Alexian Brothers entrances (Complete closure of Leicester between these two driveways. Access to Alexian Brothers and Condominiums will be maintained.)
  • Stage 4 – Complete closure of Alexian Brothers main entrance from Leicester Road (This work will take place over the weekend. The entrance will be reopened by 6:00am the following Monday.)
  • Stage 5a – Grinding and placement of the HMA surface course from Biesterfield Rd to Wellington Avenue (This work will take place over the weekend)
  • Stage 5b – Landscape restoration and roadway striping (Two-way traffic will be maintained) 

Over the next few months I will be providing you with updates on the Leicester Road Construction project in an attempt to keep everyone as informed as possible. Our goal is to complete this project with minimum disruption to everyone.  The Village thanks you in advance for your patience and understanding.  If at any time you have a concern or question, please feel free to contact me at 847-734-8077.