General Information- To Be Announced
  • Start Date: April 2025
  • Est. Completion Date: July 2025
  • Location: Bennett Road at Gaylord Street Intersection
  • Project Cost: $626,000
  • Contractor: Aqua Contractors
  • Project Impacts:
    • Moving daily lane closures
    • Temporary sidewalk closure
    • Construction vehicle presence
Project Description

In an effort to alleviate on-street flooding, the Village will be installing new parallel storm sewers in the drainage easements between 600 and 610 Bennett Road. Additional storm sewer and drainage structures will also be installed at the Bennett and Gaylord and Bennett and Gordon intersections. 

 

Project Updates

July 3, 2025: This week, the contractor completed the concrete restoration and pavement patching prior to the start of the Business Park Resurfacing

June 13, 2025: This week, the contractor completed the installation of the new drainage system. Next week, work will continue with the restoration of concrete and roadway.

June 6, 2025: This week, the contractor installed the new parallel culvert between the buildings of 600 and 610 Bennett Drive. Additionally, the water main was lowered in two locations to allow for the new storm sewer to be installed. Next week, work will continue with the installation of storm sewer and inlets on Bennett Drive at Gaylord Street.