General Information
- Start Date: July 2025
- Est. Completion Date: October 2025
- Location: Various Streets Throughout Business Park. See Below.
- Project Cost: $1,555,808
- Contractor: Builders Paving, LLC
- Project Impacts:
- Moving Daily Lane Closures
- Temporary Sidewalk Closure
- Construction Vehicle Presence
Project Description
The construction activities for the business park resurfacing program are generally broken down into four phases:
Phase I (Storm Sewer) – Necessary repairs and/or modifications are made to the drainage structures along these roadways.
Phase II (Concrete) – Replacement of deteriorated curbs and sidewalks throughout the project area takes place. This work is generally limited to one side of the street at a time.
Phase III (Pavement) – The final phase includes full depth pavement patching, milling of the existing pavement surface, paving the new asphalt surface and the painting of pavement markings. Friendly reminder: A tack-coat of fresh oil is applied prior to laying the new pavement layer as an adhesive or bonding agent between the asphalt layers. Fresh oil signage will be posted in advance to remind motorist to travel slowly on the tack-coat material.
Phase IV (Restoration) – Final restoration of all disturbed areas to be completed.
The following 2.9 miles of roadways in the Business Park are anticipated to be resurfaced starting in July and completed by October:
- Bennett Road, Arlington Heights Road to King Street
- Bonnie Lane, Howard Street to Oakton Street
- Commerce Drive, Busse Road to Higgins Road
- Estes Avenue, Busse Road to west of Elmhurst Road
- King Street, Bennett Road to Northwest Point Boulevard
Project Updates
September 5, 2025: This week, the contractor completed the road resurfacing on Bennett Drive and King Street. Next week, clean-up and punchlist work will continue throughout the project.
August 29, 2025: This week, the contractor performed full depth asphalt patches and the surface was milled on Bennett Drive and King Street. The contractor also paved the asphalt surface on Bonnie Lane, Estes Avenue, and Commerce Drive. The surface paving on Bennett Drive and King street is scheduled for Friday night. Next week, clean-up and punchlist work will occur throughout the project.
August 22, 2025: This week, concrete curbs and sidewalk were completed on Bennett Drive and King Street. The contractor also milled the pavement on Bonnie Lane, Estes Avenue, and Commerce Drive. Next week, full-depth asphalt patches will be performed on Bennett Road and King Street. Bonnie Lane, Commerce Drive, and Estes Avenue will all be paved at night.
August 15, 2025: This week, concrete curbs and sidewalk were poured on the south side of Bennett Drive and the west side of King Street. The contractor also replaced full-depth asphalt patches on Bonnie Lane, Estes Avenue, and Commerce Drive. Next week, concrete replacement as well as asphalt patching will be completed on Bennett Road and King Street.
August 8, 2025: This week, concrete curbs and sidewalk were poured on the north side of Estes Avenue and the east side of King Street. Curb and sidewalk was also removed on the south side of Bennett Road. New drainage structures were also installed on Bonnie Lane and King Street. Next week, concrete replacement will continue on Bennett Road and King Street. Asphalt patching will also begin on Commerce Drive and Estes Avenue.
August 1, 2025: This week, concrete curbs and sidewalk were removed and replaced on the west side of Bonnie Lane, and the north and south sides of Estes Avenue. Next week, concrete replacement will continue on the north side of Estes as well as the east side of King Street and the south side of Bennett Road.
July 25, 2025: This week, concrete curbs were removed and re-poured on Commerce Drive, the east side of Bonnie Lane, and the south side of Estes. Next week, concrete replacement will continue on the opposite sides of Bonnie and Estes as well as the east side of King Street and the south side of Bennett Road.
July 18, 2025: This week, the 2025 Business Park Resurfacing Project kicked off with concrete removals on Commerce Drive. Next week, concrete replacement will continue on Commerce Drive. This year’s project includes Commerce Drive, Bennett Road, King Street (Bennett to Northwest Point), Bonnie Lane (Howard to Oakton), and Estes Avenue (Busse to west of Elmhurst Road).