Business Park Resurfacing Program

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

General Information

  • Start Date: May 1, 2026
  • Est. Completion Date: September 2026
  • Location: Various Streets Throughout Business Park. See Below.
  • Project Cost: $1,518,808
  • Contractor: Builders Paving, LLC
  • Project Impacts:
    • Moving Daily Lane Closures
    • Temporary Sidewalk Closure
    • Construction Vehicle Presence

Project Description

The construction activities for the business park resurfacing program are generally broken down into four phases:

Phase I (Storm Sewer) – Necessary repairs and/or modifications are made to the drainage structures along these roadways.

Phase II (Concrete) – Replacement of deteriorated curbs and sidewalks throughout the project area takes place. This work is generally limited to one side of the street at a time.

Phase III (Pavement) – The final phase includes full depth pavement patching, milling of the existing pavement surface, paving the new asphalt surface and the painting of pavement markings. Friendly reminder:  A tack-coat of fresh oil is applied prior to laying the new pavement layer as an adhesive or bonding agent between the asphalt layers. Fresh oil signage will be posted in advance to remind motorist to travel slowly on the tack-coat material.

Phase IV (Restoration) – Final restoration of all disturbed areas to be completed.

The following 2.9 miles of roadways in the Business Park are anticipated to be resurfaced starting in July and completed by October:

ROADWAY

BOUNDARY STREETS

BRUMMEL AVENUE

LIVELY BOULEVARD

CROSSEN AVENUE

FARGO AVENUE

TONNE ROAD

LIVELY BOULEVARD

GREENLEAF AVENUE

TONNE ROAD

W. OF BUSSE ROAD

GULLO AVENUE

STANLEY STREET

END

HOWARD STREET

PERRIE DRIVE

LIVELY BOULEVARD

STANLEY STREET

OAKTON STREET

GULLO AVENUE

 

Project Updates

May 29, 2026: This week, the contractor completed the asphalt patching, roadway surface milling, and landscape restoration. Next week, the asphalt surface placement will be completed on all the streets. 

May 22, 2026: This week, the contractor completed the concrete removal and replacement for the project and began the asphalt patching on Fargo Avenue, Greenleaf Avenue and Howard Street Next week, landscape restoration will occur before the milling operation begins. 

May 15, 2026: This week, the contractor continued with concrete removal and replacement and sewer adjustments on the east side of Stanley Street, the north sides of Gullo Avenue, Greenleaf Avenue, and Fargo Avenue. Concrete replacement also took place on Howard Street and Brummel Avenue. Next week, concrete work will be completed on all streets.

May 8, 2026: This week, the 2026 Business Park Resurfacing Project kicked off with concrete removal and replacement and sewer adjustments on the west side of Stanley Street, the south sides of Gullo Avenue, Greenleaf Avenue, and Fargo Avenue. Next week, concrete work will continue on the opposite sides of Stanley and Gullo, as well as the south sides of Greenleaf and Fargo.