Meacham Rd. & Biesterfield Rd. Pedestrian Improvement

Print
Press Enter to show all options, press Tab go to next option

 

Project Description

 This summer the Village will partake in intersection improvements along Meacham Road. These improvements consist sidewalk and ADA ramp improvements, pedestrian signal modifications, and the addition of internally illuminated street name signs.

Also included in the project will be the addition of a new eight-foot multi-use path that will be constructed on the south side of Wise Road from Schooner Lane to Michigan Lane then continue on the north side of Biesterfield Road from Michigan Lane to Home Avenue. A new six-foot sidewalk will be constructed on the south side of Biesterfield Road from West Glenn Trail to David Lane and on the north side of Biesterfield Road from White Trail to Robin Drive. These multi-use paths and sidewalks work will include ADA ramp improvements at intersections when needed.

  • Start Date: July 8, 2020
  • Est. Completion Date: TBA
  • Project Cost: $794,936
  • Contractor: A Lamp Construction
  • Project Manager: Jeff Maczko, P.E.
  • Location: Intersections of Meacham Road at Nerge Road, Mallard Crossing, Biesterfield Road, and Texas Street; Along  Biesterfield/Wise Road from Schooner Lane to David Lane.
  • Project Impacts: At the intersections along Meacham Road, sidewalk corners will be reconstructed to ADA compliance.  This includes reconstructed slopes and widths on the sidewalk, as well as the location and placement of pedestrian push buttons for the traffic signals.  Also, new illuminated street name signs will be installed at these intersections.  Along the Wise/Biesterfield Road corridor, a new eight-foot shared use path will be constructed west of Home Avenue to extend the current shared use path to the Village’s western limits.  This will tie into the existing on road bike lane on Schooner Lane.  Six-foot sidewalk will replace the existing sidewalk along Biesterfiled Road from David Lane that is heavily used by walkers to Link School.  During construction, sidewalks will be closed to pedestrians to accommodate construction.  Detour signs will direct pedestrians to alternate safe walking routes.  

Construction Updates

07/10/20: This week, A Lamp Construction began work on the Biesterfield Road and Meacham Road Pedestrian Improvement Project by completing the construction layout. Next week, tree pruning and sidewalk removal will begin along Wise Road from Schooner Lane to Michigan Lane, Biesterfield Road from Michigan Lane to Home Avenue, Biesterfield Road from West Glenn Trail to David Lane. As this project is scheduled to be completed by October, daily lane closures should be expected along Biesterfield Road.

07/02/20: Next week, A Lamp Construction will begin work on the Biesterfield Road and Meacham Road Pedestrian Improvement Project. These improvements consists of sidewalk and ADA ramp improvements, pedestrian signal modifications, and the addition of internally illuminated street name signs at 4 intersections along Meacham Road (Texas Street, Biesterfield Road, Mallard Crossing, and Nerge Road). Also included in the project will be the addition of a new eight-foot multi-use path that will be constructed on the south side of Wise Road from Schooner Lane to Michigan Lane, then continue on the north side of Biesterfield Road from Michigan Lane to Home Avenue. Additionally a new six-foot sidewalk will be constructed on the south side of Biesterfield Road from West Glenn Trail to David Lane and on the north side of Biesterfield Road from White Trail to Robin Drive. These multi-use paths and sidewalks will include ADA ramp improvements at various intersections.

Have a comment, question or concern related to a Village construction project?  Click here to contact our Public Works Department.