Rotary Green Parking Lot Expansion

Print
Press Enter to show all options, press Tab go to next option

Project Description

The Village will be adding additional parking to the Rotary Green area this summer. The project includes the addition of over 40 new parking spots, arterial lighting, bollards and minor landscaping improvements.

  • Start Date: May 2020
  • Est. Completion Date: July 2020
  • Project Cost: $328,406
  • Contractor: Maneval Construction
  • Project Manager: Brian Southey, Superintendent of Administration
  • Location: Rotary Green
  • Project Impacts: Rotary Green parking lot will be closed for the duration of the project.

Construction Updates

07/10/20: This week, the contractor installed bollards along the east side of the Rotary Green’s festival grounds. 

07/02/20: Earlier today, Maneval Construction began paving the rotary green parking lot. The contractor is also scheduled to begin installing the security bollards this afternoon. Once the paving and bollard installation has been completed, the contractor will complete the installation of the parking lot lights. 

06/26/20: This week, the contractor began installing the permeable pavers as part of the Rotary Green Parking Lot Expansion project. The contractor is scheduled to continue finishing the parking lot expansion next week, followed by the installation of the new parking lot lights. 