Show/Hide

2019 Residential Street Maintenance Program

Print
Press Enter to show all options, press Tab go to next option

Project Overview

The Village's 2019 Residential Street Maintenance Program consists of curb and sidewalk rehabilitation, pavement patching, and resurfacing along 4.5 miles of residential streets, as noted below. 

Project Start: June 2019
Anticipated Completion: August 2019
Contractor:Builders Paving, LLC (Click here for Bid Tab)

Construction on the roadways listed below should begin in spring and will be completed by the end of the summer:

Phase I (Storm Sewer): Village crews will make necessary repairs to drainage structures along these roadways.

Phase II (Concrete): During the next phase the contractor will begin the removal and replacement of deteriorated curbs and sidewalks throughout the project area.

Phase III (Roadway): The final phase includes pavement patching, milling of the pavement surface and the placement of a new pavement surface layer. Just prior to laying the new pavement layer, the street will be sprayed with a tack coat. Fresh oil signs will be posted during this phase so residents are reminded to travel slowly on the tack-coated surface.

Residential Streets to be Resurfaced

  • Ash St                         Elmwood Ln to Carswell Ave                       
  • Brynhaven St              Woodcrest Ln to Wildwood Rd
  • Brynhaven Ct              Brynhaven St to End
  • Carswell Ave              Clearmont Dr to Cedar Ln                 
  • Cedar Ln                     Clearmont Dr to Victoria Ln
  • Clover Hill Ct             Wellington Ave to End          
  • Clover Hill Ln            Montego Ct to Wellington Ave
  • Grosvener Ln              Tower Ln to Victoria Ln
  • Grosvener Ct              Grosvener Ln to End
  • Grove Dr                     Perrie Dr to Perrie Dr
  • Hartford Ln                 Tonne Rd to Maple Ln
  • Maple Ct                     Cedar Ln to End
  • Oak St                         Laurel St to Tower Ln
  • Perrie Dr                     Landmeier Rd to Kent Ave
  • Tower Ln                    Elk Grove Blvd to Ridge Ave
  • Wellington Ave          Somerset Ln to Clover Hill Ln
  • Wilshire Ave               Birchwood Ave to Carswell Ave

Have a comment, question or concern related to a Village construction project?  Click here to contact our Public Works Department.

2019 Street Resurfacing Locations
Click Map for Detailed Image

MFT and Business Park Street Resurfacing 2019

Project Updates July 2019

The contractor, Builders Paving, has finished concrete work on the following streets. Next week pavement patching operations will begin on:

  • Brynhaven Street             Woodcrest Lane to Wildwood Road
  • Brynhaven Court              Brynhaven Street to End
  • Kent Avenue                    Oakton Street to Perrie Drive
  • Perrie Drive                     Kent Avenue to Landmeier Road
  • Grove Drive                     Perrie Drive to Perrie Drive


    The contractor has also begun concrete work on the following streets, and this work will continue into next week:   

  • Grosvener Lane                Tower Lane to Victoria Lane
  • Grosvener Court               Grosvener Lane to End
  • Oak Street                       Tower Lane to Laurel Street
  • Tower Lane                      Elk Grove Blvd to Ridge Avenue

Previous Construction Updates

The week of July 8, Builders Asphalt completed surface paving on the following streets:

  • Carswell Avenue           Clearmont Drive to Cedar Lane
  • Cedar Lane                   Clearmont Drive to Victoria Lane
  • Hartford Lane               Tonne Road to Maple Lane
  • Maple Court                 Cedar Lane to End
  • Wilshire Avenue            Birchwood Avenue to Carswell Avenue

    The contractor has begun concrete work on the following streets, and this work will continue into the week of July 15: 

  • Brynhaven Street               Woodcrest Lane to Wildwood Road
  • Brynhaven Court                Brynhaven Street to End
  • Kent Avenue                      Oakton Street to Perrie Drive
  • Perrie Drive                       Kent Avenue to Landmeier Road
  • Grove Drive                        Perrie Drive to Perrie Drive

The contractor, Builders Asphalt, has completed milling of the existing asphalt surface on the following streets:

  • Wellington AvenueSomerset Lane to Clover Hill Lane
  • Clover Hill LaneWellington Avenue to Montego Court
  • Clover Hill Court Wellington Avenue to End

     

    On Monday, July 1, weather permitting, placement of the new hot-mix asphalt surface will begin.  Prior to paving, an oily liquid will be applied to the milled roadway pavement to adhere the new surface to the existing pavement.  “Fresh Oil” signs are posted showing the date of this application.    

    The contractor is also finishing concrete work on the following streets:

  • Carswell AvenueClearmont Drive to Cedar Lane
  • Cedar Lane Clearmont Drive to Victoria Lane
  • Hartford LaneTonne Road to Maple Lane
  • Maple CourtCedar Lane to End
  • Wilshire AvenueBirchwood Avenue to Carswell Avenue

The week of July 1, pavement patching operations will move to these streets. 

The contractor, Builders Asphalt, has finished concrete work and roadway patching on the following streets:

  • Wellington Avenue             Somerset Lane to Clover Hill Lane
  • Clover Hill Lane                 Wellington Avenue to Montego Court
  • Clover Hill Court                Wellington Avenue to End

     

    The week of June 24 they will grind the existing roadway surface and place a new hot-mix asphalt surface.  Prior to paving, an oily liquid will be applied to the milled roadway pavement to adhere the new surface to the existing pavement.  “Fresh Oil” signs will be posted showing the date of this application.

    The week of June 24, the contractor will continue concrete work on the following streets

  • Carswell Avenue           Clearmont Drive to Cedar Lane
  • Cedar Lane                  Clearmont Drive to Victoria Lane
  • Hartford Lane              Tonne Road to Maple Lane
  • Maple Court                 Cedar Lane to End
  • Wilshire Avenue            Birchwood Avenue to Carswell Avenue

Builders Asphalt began the 2019 MFT Residential Street Rehabilitation project the week of June 10.  The contractor has begun concrete work on the following streets, and this work will continue next week on these streets:

  • Wellington Avenue         Somerset Lane to Clover Hill Lane
  • Clover Hill Lane             Wellington Avenue to Montego Court
  • Clover Hill Court            Wellington Avenue to End
  • Carswell Avenue             Clearmont Drive to Cedar Lane
  • Cedar Lane                    Clearmont Drive to Victoria Lane
  • Hartford Lane                Tonne Road to Maple Lane
  • Maple Court                   Cedar Lane to End
  • Wilshire Avenue              Birchwood Avenue to Carswell Avenue

After concrete work is completed on these streets, roadway patching and resurfacing will begin. 

The week of June 10th, Builders Asphalt will begin the 2019 MFT Residential Street Rehabilitation project.  The scope of this project includes replacing deteriorated curb and sidewalk, full depth pavement patching, and roadway resurfacing of the streets mentioned above.

The contractor will begin working on Wellington Avenue, Cloverhill Lane and Cloverhill Court first, working towards the east and north. All roads will remain open to two-way traffic during construction, but delays should be expected when crews are working.