Project Overview

The Village will be replacing the existing water main along Tanglewood Drive from Greenbriar Street to Ridgewood Road. The project includes the installation of a new 8” water main, residential service connections, pavement patching, and landscape restoration. The project is anticipated to begin construction later this spring.

Project Start: April 2019
Anticipated Completion: July 2019
Contractor: Trine Construction (Click Here for Bid Tab)

Have a comment, question or concern related to a Village construction project?  Click here to contact our Public Works Department.

Tanglewood Drive Water Main Replacement Location
Click Map for Detailed Image

Tanglewood Water Main - Location Map for Website

 

Project Updates July 2019

Parkways have been restored with sod and pavement marking were completed the week of June 24.  The project is now final and the job is complete.                

Past Updates 

Restoration of curb, sidewalk, driveways, and pavement has been completed.  The week of June 24, the contractor will be working on landscape restoration and clean up.  The project will be final the week of June 24.       

Restoration of disturbed concrete curb, sidewalk and aprons has begun and will continue into the week of June 17.  Following the concrete work, the roadway will be patched and disturbed turf areas will be restored with sod.       

Trine Construction has completed installation of the new water main.  The week of June 10, the old fire hydrants and valves will be removed from the existing water main.  Restoration work will also begin with concrete repairs to curbs, sidewalks, and aprons.      

Trine Construction has completed transferring water services from the old water main to the new water main. The week of June 3, the contractor will finish connecting the new water main to the old system at Holly Lane and Greenbriar Street.  They will also complete storm sewer replacement at Greenbriar Street and Tanglewood Drive.  Following this work, the old water main will be abandoned and restoration will be begin.        

Trine Construction has begun transferring water services from the old water main to the new water main; this work will continue through the week of May 20.  During this time, each house will be without water for a few hours as they transferred from the old main to the new main.  On Saturday, May 18, the Contractor will be making a connection to the existing water main system in the intersection of Tanglewood Drive and Ridgewood Road.  Traffic will be detoured as this work is completed.  This work is being completed on the weekend to minimize impacts to Rupley School’s driveways. 

Trine Construction has completed installation of the new water main.  The Contractor also pressure tested and chlorinated the new water main.  The week of May 13, they will begin transferring water services from the old water main to the new water main.  During this time, each house will be without water for a few hours.  Residents are notified the day before having their water service interrupted to complete this work.     

Despite the weather the week of April 29, Trine Construction has continued working on the installation of the new water main in Tanglewood Court and at the intersection of Tanglewood Drive and Greenbriar Street.  The week of May 6, the Contractor will install new fire hydrants and will begin to fill, flush, and pressure test the new water main.  Once the new main has passed the pressure testing, the new main will be chlorinated before residents will have their water services switched from the old water main to the new main.   On Wednesday, May 1, from 7:00 a.m. - 4:00 p.m. the intersection of Tanglewood Dr & Greenbriar St will be closed to all traffic. Both Holly Ln and Crest Ave should be used as alternative routes.

Trine Construction has completed installation of the new water main along Tanglewood Drive up to Ridgewood Road.  The week of April 29, they will be working to install new water main on Tanglewood Court, and at the cross streets of Greenbriar Street and Holly Lane.  They will also begin installation of new fire hydrants in preparation for filling, pressure testing, and chlorinating the new water main.   

On Monday, April 22, from 7:00 a.m. - 4:00 p.m. the intersection of  Tanglewood Dr & Greenbriar St will be closed to all traffic.

The contractor has begun installing the new water main and is progressing to the northeast along Tanglewood Drive towards Ridgewood Drive. Both Holly Lane and Crest Avenue should be used as alternative routes.

The Contractor has mobilized materials and equipment to the job site.  On Monday April 15, the Contractor will begin installing the replacement water main from the intersection of Greenbriar Street and Tanglewood Drive, working toward the east on Tanglewood Drive.  Traffic will be maintained in both directions as the contractors is installing the new water main, but delays should be expected while trucks are being loaded and equipment is working.  Residents will always have access to their driveways, except for intermittent periods as the new water main pipe is installed across their driveways.  The contractor will notify residents prior to blocking access to a driveway.