University Lane Roadway Improvement Project

Print
Press Enter to show all options, press Tab go to next option

Project Overview

The Village will be rehabilitating University Lane from Plum Grove Road to Vermont Drive. The work will consists of drainage structure repairs, full HMA pavement removal and replacement, curb and sidewalk rehabilitation and pavement markings. Construction is anticipated to begin this summer.

Project Start: June 2019
Anticipated Completion: September 2019
Contractor: Builders Paving, LLC (Click Here for Bid Tab)

Have a comment, question or concern related to a Village construction project?  Click here to contact our Public Works Department.

University Lane Roadway Improvement
Click Map for Detailed Image

University Ln Road Improvement Map

 

Project Updates July 2019

Builders Paving has begun concrete sidewalk replacement work on University Lane.  The week of July 15, the contractor will begin removing and replacing the roadway curb and gutter.  Flaggers will continue to be present to direct traffic around construction activities.  

Previous Construction Updates

The week of July 1, Builders Paving will begin concrete work at Vermont Lane and work towards Plum Grove Road on University.  Deteriorated sidewalk and trip hazards will be repaired first, then the roadway curb and gutter will be removed and replaced.  Flaggers will continue to be present to direct traffic around construction activities.

Builders Paving is preparing to begin replacement of deteriorated curb and sidewalk.  The week of June 24, the contractor will begin concrete work at Vermont Lane and work towards Plum Grove Road on University.  Flaggers will continue to be present to direct traffic around construction activities. 

Builders Paving has completed the installation of additional storm sewer on University Lane.  The week of June 17, the contractor will begin removing and replacing curb and sidewalk.  Flaggers will continue to be present to direct traffic around construction activities.

Builders Paving has begun working on the University Lane Roadway Improvements project, they are currently working on storm sewer work.  Flaggers will be present to direct traffic around construction activities. 

The scope of this project will remove and replace deteriorated curb and sidewalk, replace the entire existing asphalt pavement, add storm sewers for improved drainage, and replace all the existing street signs.  Later this summer, University Lane will go into a one-way detour to complete this work.  The project is scheduled to be completed by the end of September.   

Click here for letter distributed to area residents ahead of construction

The Week of May 27th

The contractor has begun pre-construction activities in preparation for work to begin.  Utility markings are being placed, tree protection will be installed, and saw cutting of curb and pavement will begin this week.  Please watch for workers in the construction zone and drive with caution.  

The Week of June 3rd

Sewer work will begin  between Fox Run Drive and Doral Court.  During this work, the roadway will remain open to traffic in both directions.  Flaggers will be present to direct traffic around construction operations.  Trash collection and mail delivery will continue to take place normally during the project.