University Lane Roadway Improvement Project

Print
Press Enter to show all options, press Tab go to next option

Attention:Construction Notices

CONSTRUCTION NOTICE – PRIME COAT & SURFACE PAVING

The following notice was handed out to residents on Thursday, September 19.

Dear Resident:

Final roadway paving is scheduled for Friday September 19.  Early on Friday morning (weather permitting) asphalt prime coat (“Fresh Oil”) will be placed on University Lane.  This asphalt prime coat is sprayed to prepare the existing asphalt to adhere to the new surface.  “Fresh Oil” signs will be displayed warning drivers of the prime coat.  Vehicles needing to drive on University Lane in the early morning should drive slow to reduce tracking on your vehicle.  If you are returning home early on Friday (before 8am), please be aware that the freshly sprayed material can track on your tires, and subsequently into your driveway.  You should consider parking on an adjacent street until the material has dried. 

During paving the roadway will remain open to two-way traffic, however short delays should be expected.   Flaggers will be on site to direct traffic around paving operations.  Access to your driveway will always remain open, except for the short duration the paver and rollers are passing near your driveway.  Once paving is complete past your house, you will have full access to your driveway.

If you have any questions or concerns, you may contact the Public Works Department at 847-734-8800.  Construction information may be viewed at elkgrove.org. Also, you may sign-up on the Village's website for construction e-notifications which provide project updates for construction projects within the Village. 

Thank you in advance for your patience and understanding during this vital infrastructure improvement project.

Project Overview

The Village will be rehabilitating University Lane from Plum Grove Road to Vermont Drive. The work will consists of drainage structure repairs, full HMA pavement removal and replacement, curb and sidewalk rehabilitation and pavement markings. Construction is anticipated to begin this summer.

Project Start: June 2019
Anticipated Completion: September 2019
Contractor: Builders Paving, LLC (Click Here for Bid Tab)

Have a comment, question or concern related to a Village construction project?  Click here to contact our Public Works Department.

University Lane Roadway Improvement
Click Map for Detailed Image

University Ln Road Improvement Map

 

Project Updates September 27, 2019

The project has been completed.

Previous Construction Updates

Builders Paving has completed installation of the hot-mix asphalt base over the week of September 9 and is currently working on landscape restoration.  University Lane has now been returned to two-way traffic and the detour has been removed.  Late the week of September 16, the contractor will place the new hot-mix asphalt surface and the project will be finished.  Builders Paving has completed grading the stone base in preparation for the new asphalt road.  The week of September 9, the contractor will place the new roadway pavement.  University Lane continues to be one-way in the eastbound direction from Fox Run Drive/Pebble Beach Circle to Vermont Drive.  A detour route is posted on our website for those who might be unfamiliar with the neighborhood.  It is anticipated that the detour will be in place until the end of September. 

 Builders Paving has finished complete removal of the existing asphalt roadway.  The week of September 2, the contractor will be grading the stone base in preparation for the new asphalt road.  University Lane continues to be one-way in the eastbound direction from Fox Run Drive/Pebble Beach Circle to Vermont Drive.  It is anticipated that the detour will be in place until the end of September.  

Builders Paving has finished the concrete work and will begin reconstruction of the roadway pavement the week of August 26.  This work will include complete removal and replacement of the existing asphalt roadway.  To facilitate this pavement construction, University Lane will become one-way in the eastbound direction from Fox Run Drive/Pebble Beach Circle to Vermont Drive.  A detour route will be posted for those who might be unfamiliar with the neighborhood.  It is anticipated that the detour to be in place until the end of September. 

Builders Paving will begin the final stage of concrete replacement on Monday August 19th.  They will be preforming curb work from Inverness Court to Vermont Lane on the north side of University Lane.   Flaggers will continue to be present to direct traffic around construction activities. 

Builders Paving removed and replaced the roadway curb and gutter on the north side of University Lane from Plum Grove Road to Inverness Court.  The concrete is currently curing until Monday, August 12, at which point residents will be able to return to their driveways.  Later the week of August 12, they will continue the same curb work from Inverness Court to Vermont Lane on the north side.  Flaggers will continue to be present to direct traffic around construction activities. 

The week of July 29, Builders Paving will remove and replace the roadway curb and gutter on the north side of the roadway.  This work will be done in two stages to accommodate the displacement of vehicles from driveways.  Stage 1 will replace all the curb from Plum Grove Road to Inverness Court.  Flaggers will continue to be present to direct traffic around construction activities.

The week of July 22, Builders Paving removed and replaced the roadway curb and gutter on the south side of the roadway.  After curing is completed mid next week, the contractor will begin curb removal and replacement on the north side of University Lane.  Flaggers will continue to be present to direct traffic around construction activities. 

The week of July 22, Builders Paving will begin removing and replacing the roadway curb and gutter.  The work will begin on the south side of University Lane.  Flaggers will continue to be present to direct traffic around construction activities. Builders Paving has begun concrete sidewalk replacement work on University Lane.  The week of July 15, the contractor will begin removing and replacing the roadway curb and gutter.  Flaggers will continue to be present to direct traffic around construction activities.  

The week of July 1, Builders Paving will begin concrete work at Vermont Lane and work towards Plum Grove Road on University.  Deteriorated sidewalk and trip hazards will be repaired first, then the roadway curb and gutter will be removed and replaced.  Flaggers will continue to be present to direct traffic around construction activities.

Builders Paving is preparing to begin replacement of deteriorated curb and sidewalk.  The week of June 24, the contractor will begin concrete work at Vermont Lane and work towards Plum Grove Road on University.  Flaggers will continue to be present to direct traffic around construction activities. 

Builders Paving has completed the installation of additional storm sewer on University Lane.  The week of June 17, the contractor will begin removing and replacing curb and sidewalk.  Flaggers will continue to be present to direct traffic around construction activities.

Builders Paving has begun working on the University Lane Roadway Improvements project, they are currently working on storm sewer work.  Flaggers will be present to direct traffic around construction activities. 

The scope of this project will remove and replace deteriorated curb and sidewalk, replace the entire existing asphalt pavement, add storm sewers for improved drainage, and replace all the existing street signs.  Later this summer, University Lane will go into a one-way detour to complete this work.  The project is scheduled to be completed by the end of September.   

Click here for letter distributed to area residents ahead of construction

The Week of May 27th

The contractor has begun pre-construction activities in preparation for work to begin.  Utility markings are being placed, tree protection will be installed, and saw cutting of curb and pavement will begin this week.  Please watch for workers in the construction zone and drive with caution.  

The Week of June 3rd

Sewer work will begin  between Fox Run Drive and Doral Court.  During this work, the roadway will remain open to traffic in both directions.  Flaggers will be present to direct traffic around construction operations.  Trash collection and mail delivery will continue to take place normally during the project.